6 Schedule and impacted specifications
Provide the schedule of tasks to be performed;
Document Type |
Document Number* |
Title | Schedule (TP No.) Start |
Schedule (TP No.) Change Control |
Schedule (TP No.) Freeze |
Schedule (TP No.) Approval |
Lead WG | Impacted WGs | Comments |
---|---|---|---|---|---|---|---|---|---|
TR | TR-00xx | oneM2M and MEC integration scenario and mechanisms | TP#66 | 75 | 76 | 77 | WG2 | ||
TS | TS-00xx | oneM2M and MEC interworking and deployments | TP#66 | 75 | 76 | 77 | WG2 | ||
TR | TR-00xx | Developer Guide: oneM2M and MEC deployment | TP#68 | 73 | 74 | 75 | WG4 |
- The first versions will be assigned by the secretariat (WPM Secretary)
Impacted TS/TR |
CR number (when known) | Subject of the CR | Approved at plenary# | Impacted WGs | Comments |
---|---|---|---|---|---|
TR | TR-0001 | Uses Cases | TP#77 | WG2 | |
TS | TS-0001 | Functional Architecture | TP#77 | WG2 | |
TS | TS-0004 | Service Layer Core Protocol | TP#77 | WG2 | |
TS | TS-0018 | Test and conformance | TP#77 | WG4 |